National Grid Taunton River Excavation

Dewatering and water treatment to support multiple excavations for the installation of National Grid electrical towers along the Taunton River.

 

DEWATERING

  • 200 GPM (gallons per minute) Wellpoint System with 35 wellpoints & 100 GPM Sump System

 

WATER TREATMENT

  • 200 GPM water treatment system
  • Contaminants of concern include¬†; total suspended solids (TSS)
  • System included; weir tank and dirt bag filtration